Graphs of DREG reactor parameter data from Skala computer
The most detailed, publicly available reactor data is reproduced in graph form below, based on this page from the renowned site by Viktor Dmitriev of VNIIAES: http://accidont.ru/datable.html
Some observations from the graph above:
- Remember that the reactor is split into two separate coolant loops, each with its own set of Main Circulating Pumps and Drum Separators. Therefore each parameter is listed twice, for left-hand side and right-hand side.
- The
Skala's DREG program stopped recording reactor parameters three times
that night. Just after midnight the system crashed due to a power supply
problem. The system was also manually reset twice because the control
staff intended to either delay or cancel the rundown test. One of these
Skala restarts is presumably indicated by the period of no data ending
around 1:18am. This reset could also mark a transition between the
turbine vibration test and the rundown test.
- Feedwater
is additional coolant added to the drum separators to make up for
losses to evaporation. In the case of the two large influxes of
feedwater depicted above, SIUB Stolyarchuk was likely trying to refill
the left-hand side drum separators in accordance with safety parameters.
The addition of relatively cool feedwater could depress boiling in the
core, requiring the removal of control rods. Conversely, note the
increase in feedwater temperature just before the rundown test begins,
which reflects the feedwater flow rate returning to normal. This likely
introduced positive reactivity into the core in the final minute.
- The
green lines indicate that the left-hand side drum separators suffered
from low water levels, which was the cause of periodic warning signals
during the shift. Around 1:05am the water level actually dropped below
the -700mm lower limit, hence the SIUB's urgent insertion of feedwater.
Water in the drum separators is an important reservoir for emergency
cooling in the result of an accident, but did not play a direct role in
this one.
The final minutes from the previous graph are produced above, right after the reset of the DREG program. The Main Circulating Pumps inlet temperature parameter remained constant in this period, which reminds us of the fact that the level of boiling in the core is determined by pressure. Drum separators pressure can be seen to decline and then increase by a few kg/cm^2 during the rundown test. It then skyrockets as the accident sequence begins.
The graph above depicts the only direct and unambiguous violation of safety rules that occurred that night. Most of the main circulating pumps were periodically exceeding the flow rate limit of 7000 cubic meters per hour. Flow rates were supposed to be lower during low power operation to prevent cavitation of the pumps. Studies cited in INSAG-7 found that the pumps came closest to cavitation a few minutes before the rundown test began, although it never actually occurred. Nevertheless, cavitation is the preferred culprit for the accident in papers published in the 1990s by the RBMK's design bureau (NIKIET).Why were
flow rates so high? Maintaining control of these parameters was
especially difficult at low power, and the MCPs often exhibited roving
flow rates, with one pump 'robbing' the output from another. A former
SIUB of my acquaintance speculated that Stolyarchuk set the flow rate
window to 6500-6800 m^3/hr, which made fluctuations above 7000
inevitable. With a lower setpoint of 6000, occasional fluctuations below
the automatic pump shutdown threshold of 5000 m^3/hr could have
occurred (see the next graph below).
Comments
Post a Comment